Which of the following is one of the labour costs related to actual work?
Doğru Cevap!
Yanlış Cevap!
Doğru Cevap: B) Production and Efficiency Premium
Efficient Resource Allocation Communication Coordination Time Management Motivation Which of the above are the benefits resulting from the preparation and use of budgets?
Doğru Cevap: E) I, II, III, IV and V
What contains information about the cost of direct materials used on a specific job and in a specific department?
Doğru Cevap: B) Materials requisition records
Which of the following terms refers to the volume of production or sales where total costs are equal to revenue?
Doğru Cevap: E) Break even point
Which of the following is not one of the steps in process costing?
Doğru Cevap: D) Assign predicted cost to all units under production
Which costs are generally accepted as the investments that companies incur in order to create the needed capacity?
Doğru Cevap: B) Fixed Overhead Costs
Which of the following is not one of the categories of budgets according to scope of coverage?
Doğru Cevap: E) Short-term budgets
Which one of the following is the first step of the activity-based costing?
Doğru Cevap: A) Identify the cost object
Which of the following refers to the amount of cost allocated to each unit of the allocation base?
Doğru Cevap: D) Rate
Which of the following reflects the company’s short-term plans related to the implementation of strategic projects, and result in the preparation of budgeted income statement?
Doğru Cevap: A) Operating budget
Which one of the following are the routinely repeated decisions?
Doğru Cevap: E) Programmed decisions
Which of the following is the difference between the actual results and budgeted amounts?
Doğru Cevap: A) Variance
... represents the amount of overhead cost allocated to jobs whenever a unit of allocation base is used/spent during the accounting period. Which one of the following fills the blank correctly?
Doğru Cevap: E) Allocation rate
If the operations are suggested to incur cumulatively over the years which budgeting technique is preferable?
Doğru Cevap: A) Incremental Budgeting
This type of cost is excluded from future business decisions. It doesn’t need to be taken into consideration while decision making. All costs that do not qualify as relevant costs are this type of cost. They are not related to future decisions and they do not change between various alternatives. Which type of cost is defined above?
Doğru Cevap: A) Sunk cost
Which of the following adjusts the revenues and expenses according to actual sales volume?
Doğru Cevap: D) Flexible budget
To calculate the unit cost, there is a five-step procedure of process costing. The steps are as follows: 1)Summarize the flow of physical units of output.The steps are as follows: 2)Compute the cost per equivalent unit 3)Summarize the total cost to account for 4)Compute output in terms of equivalent units 5)Assign total cost to completed units and ending work-in-process inventory Which two must change for the ranking to be correct?
Doğru Cevap: A) 2-4
Which of the following is not an objective of pricing?
Doğru Cevap: E) Advertising the company
.......................................d, which is also called as super variable costing, does not have widespread use in practice. Under this method, only the direct material cost is the product cost, while all other manufacturing related expenditures are considered as period expenses to be reported in the income statement. Which of the following should come to the dotted place according to the whole sentence?
Doğru Cevap: D) Throughput Costing Method
... also suggests covering all manufacturing factors as product cost in parallel to the full costing method; however, in this method costs of indirect manufacturing factors are allocated to products depending on the utilization rates of these factors. Which one of the following fills the blank correctly?
Doğru Cevap: A) Normal costing method